Railway Infrastructure Project Delays: a Bibliometric Analysis and Unified Classification of Contributing Factors
 
More details
Hide details
1
Faculty of Civil Engineering and Transport, PK Krakow University of Technology, Krakow, Poland
 
2
PK KUT Doctoral School, PK Krakow University of Technology, Krakow, Poland
 
These authors had equal contribution to this work
 
 
Submission date: 2026-08-23
 
 
Final revision date: 2026-10-25
 
 
Acceptance date: 2026-11-01
 
 
Online publication date: 2026-11-25
 
 
Publication date: 2026-11-25
 
 
Corresponding author
Agnieszka Leśniak   

Faculty of Civil Engineering and Transport, PK Krakow University of Technology, ul. Warszawska 24, 31-155, Kraków, Poland
 
 
Civil and Environmental Engineering Reports 2026;36(4):83-106
 
KEYWORDS
TOPICS
ABSTRACT
Timely completion of railway projects is affected by numerous interacting organisational, technical, contractual and administrative factors. This study identifies and systematises the main causes of delay through a bibliometric analysis of 32 publications selected from Scopus and a critical review of 41 sources, including additional academic sources identified outside the Scopus dataset and four reports of the Polish Supreme Audit Office (NIK). A total of 683 factor entries were extracted and, after terminological harmonisation, consolidated into 552 unique harmonised factors grouped into 12 categories. The categories containing the largest numbers of unique harmonised factors concerned project organisation and management, contractor performance, administrative decisions and approvals, and design documentation. Railway-specific factors, particularly track possessions and access to operational infrastructure, formed a relatively small category within the developed classification. The proposed classification provides a basis for comparing previous findings and for further empirical research on railway project delays.
REFERENCES (63)
1.
Aishwarya, S, Muthu, D and Venkata, SC 2019. Progress monitoring in a real time infrastructure projects. International Journal of Innovative Technology and Exploring Engineering 8, 743–747.
 
2.
Anysz, H 2012. Analiza zależności opóźnień w realizacji kontraktów na wykonanie robót budowlanych od czynników leżących poza sferą organizacji budowy i robót budowlanych [Analysis of the relationship between delays in the execution of construction contracts and factors outside the scope of construction site and construction works organisation]. In: Jemioło, S (ed) Teoretyczne podstawy budownictwa. Tom II. Procesy budowlane [Theoretical foundations of civil engineering. Vol. II. Construction processes]. Warszawa: Oficyna Wydawnicza Politechniki Warszawskiej, 69–82.
 
3.
Anysz, H and Zbiciak, A 2013. Przyczyny powstawania opóźnień w realizacji kontraktów budowlanych – analiza wstępnych wyników badania ankietowego [Causes of delays in the execution of construction contracts – analysis of preliminary survey results]. Autobusy: Technika, Eksploatacja, Systemy Transportowe 3, 963–972.
 
4.
Anysz, H and Buczkowski, B 2019. The association analysis for risk evaluation of significant delay occurrence in the completion date of construction project. International Journal of Environmental Science and Technology 16, 5369–5374. DOI: 10.1007/s13762-018-1892-7.
 
5.
Behnam, A, Wickramasinghe, DC, Ghaffar, MAA, Vu, TT, Tang, YH and Isa, HBM 2016. Automated progress monitoring system for linear infrastructure projects using satellite remote sensing. Automation in Construction 68, 114–127. DOI: 10.1016/j.autcon.2016.05.002.
 
6.
Bensalah, M, Elouadi, A and Mharzi, H 2019. Overview: the opportunity of BIM in railway. Smart and Sustainable Built Environment 8, 103–116. DOI: 10.1108/SASBE-11-2017-0060.
 
7.
Bouraima, MB, Dong, S, Aytekin, A, Qian, S and Yang, Z 2026. An Integrated T-Spherical Fuzzy Decision-Making Approach for Assessing Challenges in Belt and Road Initiative Railway Projects. International Journal of Fuzzy Systems. DOI: 10.1007/s40815-026-02248-5.
 
8.
Dziadosz, A, Rejment, M and Fojt, I 2025. Rodzaje, przyczyny i skutki opóźnień w procesach budowlanych [Types, causes and effects of delays in construction processes]. Przegląd Budowlany 96, 206–208. DOI: 10.5604/01.3001.0055.1021.
 
9.
Faustini, F 2026. Contractual frameworks in the procurement of major railway works: the case of the Kénitra–Marrakech High-Speed Rail line. Ingegneria Ferroviaria 81, 453–467. DOI: 10.57597/IF.06.2026.ART.1.
 
10.
Flyvbjerg, B 2011. Over budget, over time, over and over again: Managing major projects. In: Morris, PWG, Pinto, JK and Söderlund, J (eds) The Oxford Handbook of Project Management. Oxford: Oxford University Press, 321–344. DOI: 10.1093/oxfordhb/9780199563142.003.0014.
 
11.
Gao, S, Chan, T-K and Hendy, P 2025. Adoption of the digitalised last planner system in infrastructure projects: an Australian case study. Construction Innovation 25, 994–1013. DOI: 10.1108/CI-03-2023-0058.
 
12.
Gashaw, T and Jilcha, K 2022. Developing a fuzzy synthetic evaluation model for risk assessment: a case of Addis-Djibouti railway construction project. Innovative Infrastructure Solutions 7, 154. DOI: 10.1007/s41062-022-00753-8.
 
13.
Gashaw, T and Jilcha, K 2023. Design risk modeling and analysis for railway construction projects. International Journal of Construction Management 23, 2488–2498. DOI: 10.1080/15623599.2022.2070344.
 
14.
Gheewala, D, Chaturvedi, S and Sarkar, D 2025. Probabilistic risk analysis for elevated metro rail construction using Monte Carlo simulations. International Journal of Construction Management 25, 2585-2604. DOI: 10.1080/15623599.2025.2603423.
 
15.
Goodier, C, Zhang, Y, Lord, W and Soetanto, R 2018. Delay factors for international engineer-procure-construct (EPC) high-speed rail construction projects. Proceedings of the 34th Annual ARCOM Conference, Belfast, UK, 3–5 September 2018 – Association of Researchers in Construction Management, 490–499.
 
16.
Gopang, RKM, Imran, QBA and Nagapan, S 2020. Assessment of Delay Factors in Saudi Arabia Railway/Metro Construction Projects. International Journal of Sustainable Construction Engineering and Technology 11, 225–233. DOI: 10.30880/ijscet.2020.11.02.028.
 
17.
Güden, H and Süral, H 2014. Locating mobile facilities in railway construction management. Omega 45, 71–79. DOI: 10.1016/j.omega.2014.01.001.
 
18.
Hosseini, MR, Martek, I, Zavadskas, EK, Aibinu, AA, Arashpour, M and Chileshe, N 2018. Critical evaluation of off-site construction research: A Scientometric analysis. Automation in Construction 87, 235–247. DOI: 10.1016/j.autcon.2017.12.002.
 
19.
Ichsan, M, Isvara, W and Karim, S 2025. Monte Carlo Simulation for Enhancing the Schedule Completion Forecast of Jakarta Central Railway Station Construction Project. Applied Sciences 15, 7464. DOI: 10.3390/app15137464.
 
20.
Janowiec, F 2021. Zarządzanie ryzykiem robót dodatkowych w przedsięwzięciach budowy infrastruktury kolejowej [Risk management of additional works in railway infrastructure construction projects]. Doctoral dissertation. Kraków: Cracow University of Technology.
 
21.
Kang, L, Pyeon, J, Moon, H, Kim, C and Kang, M 2013. Development of improved 4D CAD system for horizontal works in civil engineering projects. Journal of Computing in Civil Engineering 27, 212–230. DOI: 10.1061/(ASCE)CP.1943-5487.0000216.
 
22.
Karim, S, Isvara, W and Ichsan, M 2024. Factors Affecting Delayed Implementation of Railway Station Projects: Case Studies in Indonesia. Global Business & Finance Review 29, 46–60. DOI: 10.17549/gbfr.2024.29.11.46.
 
23.
Kasravi, M, Mahmoudi, A and Feylizadeh, MR 2019. A novel algorithm for solving resource-constrained project scheduling problems: a case study. Journal of Advances in Management Research 16, 194–215. DOI: 10.1108/JAMR-03-2018-0033.
 
24.
Kidd, MP, Lusby, RM and Larsen, J 2019. Passenger- and operator-oriented scheduling of large railway projects. Transportation Research Part C: Emerging Technologies 102, 136–152. DOI: 10.1016/j.trc.2019.03.008.
 
25.
King, J, Nicholson, G and Schmid, F 2023. State-of-the-art in managing reliability in mega railway projects. A systematic literature review. Safety and Reliability 42, 60–100. DOI: 10.1080/09617353.2023.2284019.
 
26.
Kowalski, J and Połoński, M 2018. Identification of risk investment using the risk matrix on railway facilities. Open Engineering 8, 506–512. DOI: 10.1515/eng-2018-0057.
 
27.
Kowalski, J, Połoński, M and Lendo-Siwicka, M 2019. Risk factors for delays in rail investments implemented in the Design & Build contracts. MATEC Web of Conferences 262, 07007. DOI: 10.1051/matecconf/201926207007.
 
28.
Kowalski, J 2020. Harmonogramowanie inwestycji kolejowych w Polsce z uwzględnieniem ryzyka w trakcie ich realizacji [Scheduling railway investments in Poland taking into account the risk during their implementation]. Doctoral dissertation. Warszawa: Szkoła Główna Gospodarstwa Wiejskiego w Warszawie.
 
29.
Kuol, A, Gharehbaghi, K, Farnes, K, Tee, KF and McManus, K 2024. Smart adaptive technologies for intelligent transportation systems (ITS): efficient design through BIM integration. Technological Sustainability 3, 474–499. DOI: 10.1108/TECHS-02-2024-0011.
 
30.
Leśniak, A and Plebankiewicz, E 2010. Opóźnienia w robotach budowlanych [Delays in Construction Works]. Zeszyty Naukowe WSOWL 3(157), 332–339.
 
31.
Leśniak, A and Piskorz, G 2017. Potential reasons for works delays resulting from the provisions of the agreement. Technical Transactions 6, 135–143. DOI: 10.4467/2353737XCT.17.093.6569.
 
32.
Leśniak, A and Piskorz, G 2018. Czynniki opóźniające realizacje przedsięwzięć budowlanych w systemie zaprojektuj i wybuduj [Delay factors in execution of Design & Build construction projects]. Acta Scientiarum Polonorum. Architectura 17, 113–124. DOI: 10.22630/ASPA.2018.17.4.46.
 
33.
Leśniak, A and Janowiec, F 2019. Risk Assessment of Additional Works in Railway Construction Investments Using the Bayes Network. Sustainability 11, 5388. DOI: 10.3390/su11195388.
 
34.
Leśniak, A and Piskorz, G 2019. Faktory opóźnień [Delay factors]. Builder 259, 26–28. DOI: 10.5604/01.3001.0013.3441.
 
35.
Leśniak, A 2025. Analiza przyczyn opóźnień oraz modelowanie opóźnień w realizacji robót budowlanych [Analysis of the causes of delays and modelling of delays in the execution of construction works]. Kraków: Cracow University of Technology.
 
36.
Li, Q, Liu, R, Sun, Q and Wang, F 2015. Research of Automatic Progress Report Generation for Railway Construction Projects in China. Advances in Mechanical Engineering 7, 309180. DOI: 10.1155/2014/309180.
 
37.
Li, R and Roberti, R 2017. Optimal Scheduling of Railway Track Possessions in Large-Scale Projects with Multiple Construction Works. Journal of Construction Engineering and Management 143, 04017007. DOI: 10.1061/(ASCE)CO.1943-7862.0001289.
 
38.
Liao, J, Kim, HY and Shin, MH 2025. Quantitative and Qualitative Benefits of Using BIM in Design and Construction Stages for Railway Development. Buildings 15, 180. DOI: 10.3390/buildings15020180.
 
39.
Love, PED, Zhou, J, Edwards, DJ, Irani, Z and Sing, C-P 2017. Off the rails: The cost performance of infrastructure rail projects. Transportation Research Part A: Policy and Practice 99, 14–29. DOI: 10.1016/j.tra.2017.02.008.
 
40.
Macherla, URT and Vilventhan, A 2025. Identification of Dispute Causes and Analysis of Resolution Mechanisms in Metro Rail Projects Using a Fuzzy Approach. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 17, 04525064. DOI: 10.1061/JLADAH.LADR-1337.
 
41.
Martín-Martín, A, Thelwall, M, Orduna-Malea, E and Delgado López-Cózar, E 2021. Google Scholar, Microsoft Academic, Scopus, Dimensions, Web of Science, and OpenCitations’ COCI: a multidisciplinary comparison of coverage via citations. Scientometrics 126, 871–906. DOI: 10.1007/s11192-020-03690-4.
 
42.
Mittal, YK and Paul, VK 2018. Identification of critical factors for delay in metro rail projects in India. International Journal of Students’ Research in Technology & Management 6, 30–39. DOI: 10.18510/ijsrtm.2018.615.
 
43.
Mittal, YK, Paul, VK and Sawhney, A 2019. Methodology for Estimating the Cost of Delay in Architectural Engineering Projects: Case of Metro Rails in India. Journal of The Institution of Engineers (India): Series A 100, 311–318. DOI: 10.1007/s40030-019-00366-y.
 
44.
Mongeon, P and Paul-Hus, A 2016. The journal coverage of Web of Science and Scopus: a comparative analysis. Scientometrics 106, 213–228. DOI: 10.1007/s11192-015-1765-5.
 
45.
Najwyższa Izba Kontroli 2013. Informacja o wynikach kontroli. Inwestycje infrastrukturalne PKP PLK S.A. [Information on the results of the audit. Infrastructure investments of PKP PLK S.A.]. Warszawa: Najwyższa Izba Kontroli.
 
46.
Najwyższa Izba Kontroli 2022. Informacja o wynikach kontroli. Realizacja Programu Inwestycji Dworcowych [Information on the results of the audit. Implementation of the Railway Station Investment Programme]. Warszawa: Najwyższa Izba Kontroli.
 
47.
Najwyższa Izba Kontroli 2023. Informacja o wynikach kontroli. Realizacja Krajowego Programu Kolejowego w zakresie budowy systemów ERTMS/ETCS na liniach kolejowych zarządzanych przez PKP PLK S.A. [Information on the results of the audit. Implementation of the National Railway Programme regarding the construction of ERTMS/ETCS systems on railway lines managed by PKP PLK S.A.]. Warszawa: Najwyższa Izba Kontroli.
 
48.
Najwyższa Izba Kontroli 2026. Informacja o wynikach kontroli. Modernizacja wybranych linii kolejowych [Information on the results of the audit. Modernisation of selected railway lines]. Warszawa: Najwyższa Izba Kontroli.
 
49.
Ng, A and Loosemore, M 2007. Risk allocation in the private provision of public infrastructure. International Journal of Project Management 25, 66–76. DOI: 10.1016/j.ijproman.2006.06.005.
 
50.
Nguyen, T, Chileshe, N, Ho, DT, Nguyen, VT and Tran, QP 2024. Significant risks that trigger cost overruns and delays in urban rail projects: A typical case study of Vietnam. Built Environment Project and Asset Management 14, 278–295. DOI: 10.1108/BEPAM-01-2023-0027.
 
51.
Nikjow, MA, Liang, L, Qi, X, Sepasgozar, SME and Chileshe, N 2021. Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects. Sustainability 13, 9503. DOI: 10.3390/su13179503.
 
52.
Piskorz, G 2023. Analiza przyczyn i modele predykcji opóźnień w realizacjach obiektów mostowych [Analysis of the causes and predictive models of delays in bridge construction projects]. Doctoral dissertation. Kraków: Cracow University of Technology.
 
53.
Połoński, M and Kowalski, J 2017. The identification of hazards concerning the character of construction works on railway sites in Poland. Technical Transactions 5, 47–55. DOI: 10.4467/2353737XCT.17.068.6425.
 
54.
Połoński, M, Kowalski, J and Wrzesiński, G 2019. Hazards in Realization of Railway Investments Carried Out in Poland Based on Red Book FIDIC Contractual Conditions. IOP Conference Series: Materials Science and Engineering 471, 022006. DOI: 10.1088/1757-899X/471/2/022006.
 
55.
Ren, R, Hu, G, Fang, J, Tong, X and Wang, C 2025. Investment Risk Analysis of Municipal Railway Construction Projects Based on Improved SNA Methodology. Buildings 15, 4025. DOI: 10.3390/buildings15224025.
 
56.
Singh, S, Johari, S, Hasan, A and Jha, KN 2022. Risk Factors in Dedicated Freight Corridor and Mass Rapid-Transit Metro Rail Infrastructure Projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 14, 04521050. DOI: 10.1061/(ASCE)LA.1943-4170.0000531.
 
57.
Steininger, BI, Groth, M and Weber, BL 2021. Cost overruns and delays in infrastructure projects: the case of Stuttgart 21. Journal of Property Investment & Finance 39, 256–282. DOI: 10.1108/JPIF-11-2019-0144.
 
58.
Tang, Y, Liu, R and Sun, Q 2014. Schedule control model for linear projects based on linear scheduling method and constraint programming. Automation in Construction 37, 22–37. DOI: 10.1016/j.autcon.2013.09.008.
 
59.
Tavassolirizi, M, Sarvari, H, Chan, DWM and Olawumi, TO 2022. Factors affecting delays in rail transportation projects using Analytic Network Process: the case of Iran. International Journal of Construction Management 22, 2712–2723. DOI: 10.1080/15623599.2020.1819946.
 
60.
Tran, PQ, Tran, NTQ and Nguyen, PT 2020. Practical Solutions to Ensure the Schedule Management of Ho Chi Minh City Urban Railway Project in Vietnam: Survey of Expert’s Opinions. Civil Engineering and Architecture 8, 466–474. DOI: 10.13189/cea.2020.080409.
 
61.
Welde, M and Bukkestein, I 2022. Over time or on time? A study of delays in large government projects. Procedia Computer Science 196, 772–781. DOI: 10.1016/j.procs.2021.12.075.
 
62.
Wu, Z, Chen, C, Cai, Y, Lu, C, Wang, H and Yu, T 2019. BIM-Based Visualization Research in the Construction Industry: A Network Analysis. International Journal of Environmental Research and Public Health 16, 3473. DOI: 10.3390/ijerph16183473.
 
63.
Zhao, L, Zhou, G, Luo, H and Gao, Y 2026. Time-cost tradeoff optimization for railway construction project with non-preemptive activity splitting. Computers & Industrial Engineering 218, 112053. DOI: 10.1016/j.cie.2026.112053.
 